JLL / MOE Zone 6 / School portfolio

Overview

2School · Blocks A + EInspection completed 29 Jun 2026
PORTFOLIO CONDITION

Two blocks, 14 defects and 11 critical exceptions.

Block E contributes 71% of provisional repair exposure, led by fire-door access and emergency-egress controls.

29 Jun 2026 Inspection date1–2 Jul 2026 Report issued6 Areas assessed
NEEDS ATTENTION
11

Critical defects require risk-based action regardless of repair cost.

BASELINE DATA COVERAGE

What the current inspection cycle proves

1 cycleNo prior comparison
Data completeness, not compliance.Historical trend is unavailable until a second inspection cycle is loaded.
GOVERNANCE QUEUE

Approvals requiring action

2
CONDITION BY AREA

Portfolio inspection breakdown

NEN score
AreaConditionDefectsCost
RECURRING ISSUES

Most affected components

14